2022 Latest 100% Exam Passing Ratio - C_TS422_1909 Dumps PDF [Q19-Q43]

Share

2022 Latest 100% Exam Passing Ratio - C_TS422_1909 Dumps PDF

Pass Exam With Full Sureness - C_TS422_1909 Dumps with 91 Questions

NEW QUESTION 19
Which task list types can have parallel sequences?
There are 2 correct answers to this question.
Response:

  • A. Rate routings (R)
  • B. Reference operation sets (S)
  • C. Master recipes (2)
  • D. Routings (N)

Answer: A,D

 

NEW QUESTION 20
Before a user can add multiple production versions in a material master, what information should be collected?
There are 3 correct answers to this question.
Response:

  • A. Validity dates
  • B. Task list group number
  • C. BOM status
  • D. Lot sizes
  • E. Work center hierarchy

Answer: A,C,D

 

NEW QUESTION 21
Which functional capabilities does the Detailed Scheduling Board have?
There are 2 correct answers to this question.
Response:

  • A. Change sales order quantities
  • B. Undo for drag & Drop planning activities
  • C. Enter time-ticket confirmation for production orders
  • D. Change planned order quantities

Answer: B,D

 

NEW QUESTION 22
What is the first step in the MRP run?
Please choose the correct answer.
Response:

  • A. BOM explosion
  • B. Source determination
  • C. Net requirements calculation
  • D. Lot size calculation

Answer: C

 

NEW QUESTION 23
MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?

  • A. It is converted into a production order.
  • B. It is converted into a schedule line.
  • C. It is converted into a planned order.
  • D. It is converted into a reservation.

Answer: D

 

NEW QUESTION 24
You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?

  • A. Top of Red
  • B. Top of Yellow
  • C. Top of Red Base
  • D. Top of Green

Answer: D

 

NEW QUESTION 25
What does a line hierarchy in repetitive manufacturing represent?

  • A. A production line with a parallel sequence in the routing
  • B. A production line with prioritized alternative work centers
  • C. A production line with an alternative sequence in the routing
  • D. A production line with more than one work center

Answer: D

 

NEW QUESTION 26
What does it mean for the production planner when MRP works with infinite capacities?

  • A. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
  • B. MRP creates capacity requirements only if the work center has sufficient capacity.
  • C. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
  • D. MRP creates capacity requirements without checking the capacity of a work center.

Answer: D

 

NEW QUESTION 27
Which options are available for an SAP S/4HANA deployment?
There are 2 correct answers to this question.
Response:

  • A. SAP S/4AHANA Enterprise Management cloud
  • B. SAP S/4HANA Professional services cloud
  • C. SAP S/4HANA on premise
  • D. SAP S/4HANA private cloud

Answer: C,D

 

NEW QUESTION 28
Where do you maintain the duration of a product on operation?

  • A. Bill of material (BOM)
  • B. Material master
  • C. Work instructions
  • D. Routing

Answer: D

 

NEW QUESTION 29
In a first step you have created master recipes. In which sequence are the additional objects created?
Please choose the correct answer.
Response:

  • A. Process order
    Control recipe
    Process message
    PI sheet
  • B. Process message
    Control recipe
    Process order
    Process message
    PI sheet
  • C. Control recipe
    Process order
    PI sheet
  • D. Process order
    Control recipe
    PI sheet
    Process message

Answer: D

 

NEW QUESTION 30
Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What is the impact of this decision? Note: There are 3 correct answers to this question.

  • A. Storage location MRP areas are required.
  • B. Sales order-specific planning run is required.
  • C. Sales order-specific stock is created
  • D. Net requirements calculation is sales order-specific.
  • E. Production orders are created with sales order reference.

Answer: C,D,E

 

NEW QUESTION 31
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?

  • A. Use the fixed lot size procedure.
  • B. Use the reorder point.
  • C. Use the minimum order quantity.
  • D. Use the MRP type for vendor managed inventory.

Answer: A

 

NEW QUESTION 32
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

  • A. Back flushing
  • B. Production order release
  • C. Kanban
  • D. Material requirements planning

Answer: D

 

NEW QUESTION 33
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.

  • A. Add the agreement to the source list and mark it for MRP relevance.
  • B. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
  • C. Add the agreement to the quota arrangement and mark it for MRP relevance.
  • D. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

Answer: A,B

 

NEW QUESTION 34
Which technological advances enabled the development of SAP S/4HANA as the digital core?
There are 3 correct answers to this question.
Response:

  • A. Multi core processors enabling parallelism of tasks
  • B. Advances in the three-tier architecture approach
  • C. Wide adoption of web standards such as Service oriented architecture
  • D. Capability to add to server landscape and scale
  • E. Big and affordable memory

Answer: A,D,E

 

NEW QUESTION 35
Which of the following is an advantage of MRP Live and NOT available in classical MRP?
Response:

  • A. MRP Live can propose alternative solutions
  • B. MRP Live can plan materials with recursive BOMs
  • C. MRP Live can create production orders automatically
  • D. MRP Live can priorities demand from sales orders

Answer: A

 

NEW QUESTION 36
Which SAP solutions are part of the Digital Value Network portfolio?
There are 3 correct answers to this question.
Response:

  • A. SAP Hybris
  • B. SAP Human Capital Management
  • C. Concur
  • D. SAP Visual Enterprise
  • E. SAP Fieldglass

Answer: A,C,E

 

NEW QUESTION 37
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.

  • A. Cost-related
  • B. Milestone-related
  • C. Product-related
  • D. Order-related

Answer: C,D

 

NEW QUESTION 38
What are the possible results of a production planning run in Advanced Planning (PP/OS)? Note: There are 3 correct answers to this question.

  • A. Stock transport order
  • B. Production order
  • C. Purchase requisition
  • D. Scheduling agreement schedule line
  • E. Planned order

Answer: C,D,E

 

NEW QUESTION 39
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.

  • A. Creation of dependent requirements
  • B. Change of the storage bin
  • C. Creation of a sales order
  • D. Change of the material's procurement type
  • E. Creation of a purchasing contract

Answer: A,C,D

 

NEW QUESTION 40
Which warehouse management functions are available in SAP EWM but NOT in SAP WM?
There are 3 correct answers to this question.
Response:

  • A. Handling Unit Management
  • B. Yard Management
  • C. Expected goods receipt
  • D. Slotting
  • E. Labor Management

Answer: C,D,E

 

NEW QUESTION 41
Which of the following business processes are controlled by parameters that are dependent on production order type? Note: There are 2 correct answers to this question.

  • A. Inspection during production
  • B. Engineering change management
  • C. Planning
  • D. Implementation

Answer: C,D

 

NEW QUESTION 42
Which data model changes have been implemented in Sales and Distribution?
There are 3 correct answers to this question.
Response:

  • A. Elimination of output condition tables
  • B. Elimination of customer master tables
  • C. Elimination of document index tables
  • D. Elimination of status tables
  • E. Elimination of LIS tables for rebates

Answer: B,C,D

 

NEW QUESTION 43
......


SAP C_TS422_1909 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Master Data in SAP S/4HANA > 12%

Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version.

Material Requirements Planning in SAP S/4HANA 8% - 12%

Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures.

Demand Management in SAP S/4HANA < 8%

Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning.

Production Orders in SAP S/4HANA > 12%

Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation.

Introduction to SAP S/4HANA Production Planning < 8%

Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning.

Process Orders in SAP S/4HANA < 8%

Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP).


 

Verified C_TS422_1909 dumps Q&As - 100% Pass from Prep4King: https://www.prep4king.com/C_TS422_1909-exam-prep-material.html