2022 100% Free PRINCE2-Foundation Daily Practice Exam With 310 Questions
PRINCE2-Foundation exam torrent PRINCE2 study guide
How much PR2F Exam Cost
The price of the PR2F exam is $176 USD.
How much PRINCE2-Foundation: PRINCE2 Foundation Exam Cost
The PRINCE2 Foundation accreditation expired after three years. You may either retake a PRINCE2 Foundation Exam before the expiry date or maintain your certification using CPD points and digital badges to ensure that your Foundation status does not have defects. If you choose for CPD travel, you have to buy MY PRINCE2 membership that costs £85 + VAT a year.
NEW QUESTION 114
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.
- A. the project board has agreed the project strategies
- B. the project mandate has been approved by the project board
- C. corporate, programme management or the customer have authorized a project
- D. the 'starting up a project' process is completed
Answer: D
Explanation:
Explanation/Reference:
Reference https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp
NEW QUESTION 115
Which should be provided by a project mandate?
- A. Initiation Stage Plan
- B. Terms of reference
- C. Detailed Business Case
- D. Stage tolerances
Answer: B
NEW QUESTION 116
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
- A. Throughout each stage
- B. In exception situations
- C. At the start of the project
- D. When a change is raised
Answer: A
Explanation:
Explanation/Reference:
Reference https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/
NEW QUESTION 117
Upon what environment is PRINCE2 based?
- A. Customer/supplier
- B. Configuration
- C. Programme
- D. Operational
Answer: A
NEW QUESTION 118
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
- A. Directing a Project
- B. Closing a Project
- C. Managing a Stage Boundary
- D. Controlling a Stage
Answer: C
Explanation:
Section: Volume B
NEW QUESTION 119
Which role is responsible for creating Checkpoint Reports?
- A. Project Support
- B. Change Authority
- C. Senior Supplier
- D. Team Manager
Answer: D
Explanation:
Section: Volume B
Explanation
NEW QUESTION 120
What information should be recorded in the quality register?
- A. Off-specifications that will occur during the project
- B. Lessons that the project will capture and use during the project
- C. Potential threats to the project's objectives and how they will be managed
- D. Planned activities to determine whether the products are fit for purpose
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: https://mplaza.pm/prince2-quality-register-template/
NEW QUESTION 121
Where should an off-specification be recorded?
- A. Configuration Management Strategy
- B. Work Package
- C. Issue Register
- D. Risk Register
Answer: C
NEW QUESTION 122
Which is created during the Starting up a Project process?
- A. Project management team role descriptions
- B. Project mandate
- C. Communication Management Strategy
- D. Quality Register
Answer: A
NEW QUESTION 123
Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?
- A. Creating a product flow diagram
- B. Writing the product description
- C. Writing a project product description
- D. Documenting the plan
Answer: A
NEW QUESTION 124
Which is a purpose of the Plans theme?
- A. Assess and control uncertainty
- B. Establish the project's structure of accountability
- C. Identify, assess and control any potential changes to the baseline
- D. Understand whether the targets are achievable
Answer: D
NEW QUESTION 125
Which is a purpose of a quality register?
- A. To identify corrective actions that are required after an audit by quality assurance
- B. To issue a unique reference number for each product
- C. To detail the number and type of quality activities to be conducted
- D. To record the quality management approach for a product
Answer: C
Explanation:
Explanation
Reference http://prince2.wiki/Quality#The_Quality_Register
NEW QUESTION 126
Which is one of the six aspects of project performance that needs to be managed?
- A. Security
- B. Risk
- C. Change
- D. Progress
Answer: B
Explanation:
Section: Volume A
Explanation
NEW QUESTION 127
Which is an objective of the quality review technique?
- A. To determine the quality responsibilities of a project team
- B. To baseline a product
- C. To provide a common understanding of what products a project will create
- D. To define the quality methods required within a project
Answer: B
NEW QUESTION 128
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,
- A. Neither 1 or 2 are true
- B. Only 2 is true
- C. Both 1 and 2 are true
- D. Only 1 is true
Answer: A
NEW QUESTION 129
Which statement defines a risk?
- A. A certain event occurring in the future that will have a negative impact on the project's objectives
- B. An event that has already occurred that the Project Manager must deal with immediately
- C. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
- D. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 130
......
Use Valid New PRINCE2-Foundation Test Notes & PRINCE2-Foundation Valid Exam Guide: https://www.prep4king.com/PRINCE2-Foundation-exam-prep-material.html
PRINCE2-Foundation Actual Questions Answers PDF 100% Cover Real Exam Questions: https://drive.google.com/open?id=1j01viwYSf1SEm5muCuMJaK17VwdrEFKA